2012 WATER DISTRIBUTION IMPROVEMENT WORK SCHEDULE

James Peterson & Sons (sub-contractor) Bill Siler Contracting 4-16 to 4-30 JASBERG STREET (M203) * New water main across MD203 to Campground 4-16 to 4/20 LYNN STREET *Ingot to Prospect 4-30 to 5-28 ASH STREET * Ingot to Prospect 5-21 to 6/25 ETHEL AVENUE *from Ohio St.73 feet North on Ethel *Ingot to Hill 5-28 to 6-18 MAPLE STREET *from Poplar 240 feet East 6/25 to 7-23 SUMMIT STREET *FROM Elevation 460 feet East on Summit 7/2 to 7/23 MILL STREET *W. Water to Lake Ave 7/9 to 8/13 CALUMET ST. - CEDAR ST. -HANCOCK ST *Calumet (Anthony to Cedar) *Cedar (Calumet to Hecla) *Hancock ( from Scallon West to end of Hancock 4-16 to 9/10 **Hydrants and Valves 4/23 to 9/17 ** Restoration Dates may change as the project moves forward. Siler Contracting Questions Call: 482-8518 Office 370-8518 Site