BRIDGE CLOSURES: Traffic Impacts

*One 10-hour closure (with ramp for emergency vehicles) WHEN? Jan. 17th, 2015, nighttime (9pm-7am) with an alternate date of Jan 24th in case of weather delay. WHY? Disconnect lift cables from lift span. *Eight 2-hourclosures WHEN? January 2015, nighttime (2am-4am) WHY? Remove balance chains *168 intermittent 15-20 minute closures WHEN? January - March 2015, nighttime (7pm-6am) WHY? Lift cable removal and reinstallation *One 11.5 hour closure (with ramp for emergency vehicles) WHEN? March 21, 2015, nighttime (8pm-7:30am) with an alternate date of March 28th in case of weather delay. WHY? Connect lift span to new cables *Eight 2-hour closures WHEN? March 2015, nighttime (2am-4am) WHY? Install balance chains.